This project comprised a courtyard and car park upgrade.

AMOUNT: $1.2 million  

DURATION: Completed in 12 weeks

PRINCIPLE: Western Sydney University

The scope of works included demolition and relocation of services, excavation, new stormwater drainage, installation subbase and base course, new kerb and gutter, construction of footpath, block and brick works, a new concrete car park, line marking, and landscape works.

 