This 10 week project involved the construction of a 500mm thick concrete heavy duty pavement for aircraft parking bay over an existing tributary or Alexandria Canal.

Drainage into the canal was maintained by the installation of four (4) 1200mm diameter concrete pipes encased in concrete. Other elements of the project included drainage pits and retaining walls.